Moreno aide visits Bowerston to discuss water plant relocation
The current treatment plant was constructed in the early 1950s, with upgrades in the 1980s and 1990s
From left are Jeremiah Warner, utility operator; Juli Stephens, southwest regional director for Sen. Bernie Moreno; Mayor Paula Beamer; and Matt Miller of WE Quicksall Engineering.
Jacquie Humphrey
On Thursday, Dec. 18, Juli Stephens, southwest regional director for Sen.
Bernie Moreno, visited the village of Bowerston.
Stephens met with Mayor Paula Beamer, Village
Administrator Bart Busby, Utility Operator Jeremiah Warner and Matt Miller of
WE Quicksall Engineering to discuss Bowerston’s water treatment plant
relocation project.
Beamer and her team took Stephens on a tour of
the plant’s current location, which is in a flood easement zone near the
village’s community park. The current treatment plant was constructed in the
early 1950s, with upgrades in the 1980s and 1990s.
The service area for the facility includes the
villages of Bowerston and Leesville, the Conotton Valley Local School District,
and the LJ Smith Stair Company, encompassing areas in both Harrison and Carroll
counties.
The current location is in a 100-year
floodplain and has seen the access road to the plant blocked by floodwaters 14
times in the past 20 years. Most notably, in February 2022, floodwater entered
the treatment plant, at which time the Environmental Protection Agency issued a
notice of violation.
Although Beamer and her team were at that time
involved in major projects for improvements to both the water distribution
system and the wastewater facility, they also began seeking funding to relocate
the treatment plant.
The village purchased real estate off Main
Street in 2023, the former site of the elementary school, in hopes of moving
the plant to higher ground.
During the sit-down portion of the meeting,
Stephens reported that she had submitted through Moreno’s office
“$1,000,000 in discretionary spending” for the proposed treatment plant and
that she is currently “waiting on appropriation budgets to pass.” The
preliminary cost for the project is estimated at $6,000,000.
Busby said “it’s not a matter of if, but when,
the next flood will happen,” and Beamer agreed that the project is “critically
important to the village, and all utility customers.” Although all funding is
not yet in place, Miller said the project will “most likely be ready to go to
construction in early 2027.”